For a process where takt time is 50 seconds and the pitch is the product of takt time and pack-out quantity, which option correctly states the pitch when the pack-out quantity is 1?

one unit every 54 seconds

one unit every 10 seconds

one unit every 57 seconds

one unit every 50 seconds

Pitch is the time interval between producing consecutive units, determined by multiplying the takt time by the pack-out quantity. With a takt time of 50 seconds and a pack-out quantity of 1, the pitch is 50 seconds. That means one unit is produced every 50 seconds. The other options would require a different pack-out quantity or takt time, so they don’t fit the given values; only 50 seconds aligns with pack-out of 1.

Next question

Find the option that is right for you!

All options are one-time payments.

$12.50

30 day premium pass

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
👑$30.00 $87.50 usd

6 month DELUXE pass (most popular)

Everything with the 30 day premium pass FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • Everything included in the premium pass
  • $87.50 usd value for $30.00! You save $57.50!
  • + Access to the ultimate digital PDF study guide
  • + 6 months of premium pass access
  • + Priority support
$12.50 $18.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy